New Growth Installation

Picture 7

Picture 6

Picture 5

Picture 4

Picture 3

Picture 2

8:00 AM I arrived, met Deb and Fin, and we started drilling out the holes. 8 holes, 3 ft deep x 1 ft diameter, with two being “long holes”: 1 ft wide x 2 ft long. Cleaned up the holes with shovels.

9:20 AM Mike arrived with sonotubes. We widened some of the holes and inserted the sonotubes.

10:00 AM Eric and Chris arrived with the sculptures. We started putting them in their respective holes, staking them, and wrapping plastic around the bottom to protect from concrete splashes.

10:45 AM Concrete truck arrived. Mike and Eric started filling holes while Chris and I continued to place and stake them. Cleaned up the concrete a little.

12:15 AM Concrete truck left. Cleaned the wheelbarrows and shovels, gathered tools. Ate lunch.

Hand Painting

Chris is hand painting two of the most graphically simple trees. The process is this:
1. Project image onto plywood
2. Trace
3. Make stencil with blue tape while watching Law & Order
4. Paint
5. Remove tape

20130524-130356.jpg
20130524-130739.jpg

Test Prints & Symmetrical Marbles

On Friday I took two buses to an office park in Carlstadt, New Jersey and then walked a quarter mile to Color X. Marshland on my left, office buildings on my right.

Picture 7

Once I entered, the first thing I noticed was the floor. Marbles. Symmetrical marbles.

Picture 6

Phone books –> vector files –> large prints on plywood.

Picture 1

Test Prints… The white pigment is in a separate cartridge, and there’s a special process for applying it.

Picture 4

After I was pleased with the colors, I ran off to work, and Chris picked the finished prints up that afternoon.

Picture 5

Please Note: Fun is to be had by walking to the left.

Administration

I want to post an update about New Growth, but there isn’t anything to look at yet. Because I’m having things fabricated, my role is solely administrative so far. I’ve been sending a lot of emails, and I’ve also attended some meetings. I’ve chosen a site. Okay, I guess you can look at a picture of the site:

photo

Here is a list of communications that I’ve sent about this project since I got back from California nearly 2 weeks ago:

April 2:
Email to Chris (fabricator), 8:06 PM

April 3:
Text Message to Chris, 7:07 PM
Text Message to Chris, 7:31 PM
Email to Chris, 9:26 PM
Email to Gary (digital printer), 9:54 PM

April 4:
Email to Gary, 8:13 AM
Email to Gary, 8:20 AM
Text Message to Chris, 9:50 AM
Email to Anne (of RIPA), 4:13 PM
Email to Anne, 10:16 PM

April 5:
Email to Anne & Lia (of Bronx Museum), 2:47 PM

April 7:
Email to Anne, 3:25 PM
Text Message to Chris, 4:15 PM
Text Message to Chris, 5:11 PM
Email to Gary, 9:02 PM

April 8:
Email to Gary, 8:00 AM
Email to Gary, 3:06 PM
Email to Anne, 6:31 PM

April 9:
Email to Gary, 4:53 PM
Email to Gary, 8:33 PM

April 10:
Email to Anne & Lia, 10:08 AM
Email to Anne & Lia, 12:03 PM
Email to Gary, 12:40 PM
Email to Anne, 2:21 PM
Email to Anne, 2:32 PM
Email to Anne, Deb, Scott & Eric (all of RIPA), 3:08 PM
Email to Anne, Deb, Scott & Eric, 3:14 PM
Email to Gary, 3:16 PM
Email to Deb, 3:25 PM
Email to Deb, 3:29 PM
Email to Deb, 3:30 PM
Text Message to Chris, 7:01 PM

April 11:
Email to Deb, 9:43 AM
Email to Deb, 10:45 AM

April 12:
Email to Deb, 12:38 AM
Meeting with Deb, 8:00 AM
Email to Anne, 10:03 AM
Email to Anne, 10:27 AM